04 · AIR5 min

SUMTER FIELD DESK

Backup or power plant?

What if it generates power on site?

Short answer

Occasional emergency backup has different effects from regular generation. Engines or turbines running for months because grid service is delayed or inadequate would function as an on-site power plant, even if described as “temporary” or “mobile.”

Three numbers officials need

  1. Normal facility demand - how much power the campus normally uses.
  2. Installed generating capacity - often larger because of redundancy.
  3. Allowed operating hours - the difference between rare backup and routine pollution.

Diesel scale scenario

A representative Caterpillar 3516B has a 1.64 MW continuous rating and uses about 119 gallons of diesel per hour at that rating. Scaling comparable engines to 100 MW of continuous output gives approximately:

MeasureApproximate amount
Diesel per hour7,300 gallons
Diesel per day175,000 gallons
Diesel per year63.6 million gallons
Direct CO₂ per year650,000 metric tons
Passenger-car CO₂ equivalent140,000 typical cars

This scenario assumes continuous operation and is not a forecast for the Americus project.

Natural-gas turbine scale scenario

A representative 16.53 MW turbine with a 9,630 Btu/kWh heat rate scales to approximately:

Measure at 100 MW continuous outputApproximate amount
Gas per hour963,000 cubic feet
Gas per day23.1 million cubic feet
Gas per year8.44 billion cubic feet
Direct CO₂ per year450,000 metric tons
Passenger-car CO₂ equivalent98,000 typical cars

Natural gas usually emits less direct CO₂, particulate matter, and sulfur pollution than diesel per unit of electricity, but it still emits NOx, CO, VOCs, hazardous pollutants, and CO₂. Upstream methane is outside the stack calculation.

Limits of the car comparison

The car comparison describes annual CO₂ scale only. Cars spread emissions over many roads; a generator plant concentrates emissions at one property. Local health analysis requires unit-specific emission rates, stack heights, operating hours, weather, and dispersion modeling for NO₂, particulate matter, CO, VOCs, and hazardous pollutants.

Questions that close the loopholes

The signed development agreement states that backup generators “shall be used only in emergency situations” and limits routine testing to 8:00 a.m. through 6:00 p.m., Monday through Friday (§10). It does not define “emergency,” cap annual testing days or identify the engines, fuel and emission controls. The following conditions would supply those details.

The zoning ordinance signed October 24, 2026 limits generators to "backup/ emergency use only," except for testing, maintenance and commissioning, and keeps them away from residential and agricultural neighbors and out of buffers and setbacks (§94-159(d)(2)). The city code addition signed October 22 requires them to be screened and at least 100 feet from adjacent property lines (Sec. 14-405), and requires a Georgia Power or other supplier letter confirming capacity before a permit (Sec. 14-409).

Neither defines "emergency," caps testing hours, or sets an emission standard. Neither addresses "bring your own generation," a data center building or contracting its own dedicated generating capacity instead of waiting on utility interconnection.

There are claims that BYOG will be prevented by the use of a "refusal of occupancy permit" if they don't have permanent power from the utilities. This is only word of mouth at this point.

  • List every engine and turbine by model, rating, fuel, controls, and location.
  • Separate hours for testing, outages, demand response, peak shaving, and delayed grid connection.
  • Define “emergency” narrowly.
  • Model simultaneous testing and credible outage operation.
  • Aggregate temporary, mobile, phased, and commonly controlled equipment.
  • Require public hour-meter, fuel, and emissions records.
  • Do not allow occupancy before firm grid service without separate approval as a power plant.

The equipment schedule and any air-permit application are records held by the county and Georgia EPD. See how to obtain the records and reach the officials, and the contact page for the same roster with each official's published e-mail address.

Relevant precedent

An official Irish filing illustrates why residents should ask whether generation is truly for emergencies. It describes temporary gas engines followed by nine permanent dual-fuel engines, with seven serving normal load, selective catalytic reduction, and continuous emissions monitoring. This is an example from South Dublin Routing 4 No. 2 Limited, not evidence about the Sumter County proposal.